Projects

Moorcroft Water and Sewer Improvements, Moorcroft, Wyoming

JR Civil performed the waterline and sanitary sewer improvements project in Moorcroft, Wyoming.  The project consisted of approximately 4,000 lf of 8” waterline and 2,500 lf of 8” sanitary sewer including temporary water, sanitary sewer bypass, surface removals, road reconstruction and concrete surface improvements.

Pine Haven Sanitary Sewer Improvements, Pine Haven, Wyoming

JR Civil completed the sanitary sewer improvements project in Pine Haven, Wyoming.  This project consisted of the construction of approximately 3,000 lf of 8” sanitary sewer with excavation depths of 25’.  

Harmony Ditch Relocation, Manderson, Wyoming

JR Civil performed the intake structure installation and relocation of Harmony Ditch Fish Bypass in Manderson, Wyoming for the Wyoming Fish and Game on the Nowood River.  Construction consisted of approximately 2,000 lf of 42” pipe, Intake Structure construction and earthwork for ditch reconstruction including reconstruction of the Nowood River banks utilizing wood toe stabilization.  

Water Main Replacement Project, Buffalo, South Dakota

JR Civil performed the replacement of approximately 18,000 lf of 6” and 8” water main replacement for the Town of Buffalo, South Dakota.  This project includes water main installations, fire hydrants, water main fittings and tie ins to existing mains, asphalt pavement replacement, concrete curb and gutter replacement, temporary water, service line reconnections, landscape repairs and seeding.

Peach Street Improvements, Bozeman, Montana

JR Civil is performing the reconstruction of approximately four blocks of Peach Street including regrading the existing road profile, curb and gutter, asphalt construction, waterline improvements, storm drainage improvements, sanitary sewer line reconstruction, striping and signage.

Tioga Main Street North Extension, Tioga, North Dakota

JR Civil constructed the extension of Main Street in Tioga, North Dakota.  Improvements included 2,000 lf of 12” and 8” sanitary sewer with a direction drill bore of 24” casing under Signal Road, including all manholes and service line connections.   Storm Drainage included 48” and 18” RCP pipe with inlets and manholes.  Waterline Improvements included 1,800 lf of 12” C-900 including all service connection saddles, corporation stops, 1” service line and curb valves for the domestic services.  JR Civil installed 3,400 lf of curb & gutter, 6,700 CY of structural import base material 3,200 tons of aggregate base course and 2,600 tons of asphalt pavement.

Richardton Health Care Facility, Richardton, North Dakota

JR Civil constructed the site work and utilities on a new 4 acre health care facility in Richardton, ND.  Improvements included earthwork, grading, 2,150 lf of sanitary sewer force main, package lift station and valve vault, storm drainage, 2,000 lf of 8” domestic water improvements, foundation excavation, backfill, parking lot aggregate installation and concrete pavement replacement.  

Lateral 38 A, Arapaho, Wyoming

JR Civil constructed the installation of 2,000 lf of 36” irrigation line including drop structures, diversion boxes and flume structure for the Eastern Shoshone and Northern Arapaho Tribe.

Lincoln Ave. Water and Sewer Improvements, Sinclair, Wyoming

Construction on this project consisted of rehabilitation of water and sewer improvements on Lincoln Avenue.  Improvements included approximately 5,000 lf of 8” water main, 4,000 lf of 12” sanitary sewer main and    7,000 sy of asphalt pavement.  

Dickinson Water Booster Pump Stations, Dickinson, North Dakota 

JR Civil constructed two water booster pump stations for the City of Dickinson.  The projects included concrete, mechanical piping, pump station buildings, site piping, fencing, electrical and backup generators.

Tank Water Line Improvements Project, Dunn Center, North Dakota

JR Civil performed approximately 3,900 lf of new 10” water line construction and 1,500 lf of 8” sanitary sewer line rehabilitation for the Town of Dunn Center, North Dakota.

Marriott Hotel Improvements, Dickinson, North Dakota

JR Civil constructed all site improvements for a new Marriott Hotel location in Dickinson, ND.  This project included 2,800 lf of 8” water main, 3,400 lf of 8” sanitary sewer, 35,000 cy of mass excavation and site grading, 12,000 tns of aggregate base course, curb & gutter construction, hotel foundation walls and base slab, sidewalk improvements, 2,890 lf of 18” storm drain improvements.  All concrete improvements were performed in winter conditions requiring heat and cover with an on time completion.

Dakota Prairie Refinery High Service Booster Station, Dickinson, North Dakota

JR Civil performed all site work installations for the Dakota Prairie Refinery Pump Station including a 35’ deep excavation and stabilization, 1,200 lf of 30” sanitary sewer and manhole installations, site grading and aggregate base installation, approximately 900 lf of 18” water main with tie ins to existing main for a re-route of the existing location.

Tioga Water Main Extension, Tioga, North Dakota

JR Civil performed the installation of approximately 6,200 lf of 12” water main for the Town of Tioga, North Dakota. This project included asphalt restoration, curb and gutter construction, fire hydrants, water main installation, fittings and water main reconnections.

Water and Sewer Extension Project, Dunn Center, North Dakota

JR Civil performed the construction of the water and sanitary sewer extension project for Dunn Center, North Dakota. This project included approximately 3,000 lf of 8” water line, 3,500 lf of 8” sanitary sewer construction,
fire hydrants, fittings, water service installations, manholes, road regrade and resurface.

Tioga Lagoon Access Road Construction, Tioga, North Dakota

JR Civil performed the construction of a new lagoon access road for the Town of Tioga, North Dakota.  This project included 12,000 cy of earthwork, gravel road construction and storm drainage improvements.

Tesoro Logistics Facility: Dickinson, ND

Construction of a new 8 acre truck parking and maintenance facility for Tesoro Logostics consisting of earthwork, grading, sanitary sewer, storm drainage, domestic water improvements and aggregate installation, and a package wastewater treatment facility.

Bakken Suites Water and Sewer Expansion Project: Watford City, ND

Construction of this project included the expansion of water, sewer, and storm drainage for Bakken Suites Man Camp. Waterline construction consisted of 8,500 lf of 8” waterline including fire hydrants, fittings, service line installation and tie into existing water connections, chlorination and testing. Sanitary sewer improvements included approximately 6,000 lf of 8” sanitary sewer with all manholes, service line connections and cleanouts. Sanitary sewer installation depths ranged from 8’ to 20’ with a tie in to an existing lift station. Storm drainage improvements consisted of 500 lf of 12” RCP pipe.

Candlewood Suites: Dickinson, ND

JR Civil constructed two new street extensions to facilitate a new hotel facility for Candlewood Suites. The project consisted of a new development and construction of a new city street extension. The city street extension consisted of complete new construction of Simms Street and Second Street in Dickinson, ND. Improvements included sanitary sewer, storm drainage, domestic water improvements, earthwork, street grading and roadway aggregate installation. Waterline installation included 1,200 lf of 10” waterline including live tap connections, fire hydrants, service lines and connections, chlorination and testing. Sanitary sewer improvements consisted of 1,800 lf of 8” sewer line with depths averaging 12’.

Wheatland Hills Subdivision: Culbertson, MT

Construction of a new 45 acre subdivision development for a new housing project consisted of 142 lots of residential units. Improvements included 6,873 lf of 10” and 8” sanitary sewer ranging in depths of 20’ to 12’ including all manholes and service line connections. Sanitary sewer had to be extended from the towns existing system through the municipality to the new subdivision location. Storm drainage included 24” and 18” RCP pipe with inlets and manholes. Waterline improvements included 9,154 lf of 8” C-900 including all service connection saddles, corporation stops, 1” service line and curb valves for the domestic services. JR Civil installed 7,900 CY of aggregate base course and 2,320 TNS of asphalt pavement.

Halliburton Field Camp Facility: Dickinson, ND

This project consisted of the complete site work construction for a 40 acre facility including, parking, truck wash building, chemical building, administration headquarters, truck maintenance shop and baroid facility. An overview of this project entailed approximately 100,000 CY of earthwork, soil stabilization with geogrid, 75,000 TNS of aggregate surfacing and storm drainage, waterline installation, all wet utilities. Waterline construction consisted of approximately 5,200 lf of 10”, 8”, and 6” C-900, 14 fire hydrants, fittings, services and municipal tie in connections to existing water lines. Sanitary sewer improvements consisted of 6,400 lf of 8” SDR 35 ranging in depths of 9’ to 14’ including trench dewatering, Type II bedding and import backfill material. Storm drainage improvements included 4,300 lf of RCP pipe installation with sizes ranging from 48” to 24” including outlet structures, manholes, inlets and Rip Rap channel.

White Oak Housing Development: Mandaree, ND

JR Civil constructed two new housing developments in Mandaree, ND. Improvements included sanitary sewer, storm drainage, domestic water improvements, earthwork, street grading and roadway aggregate installation. Waterline installation included 1,400 lf of 8” waterline including live tap connections, fire hydrants, service lines and connections, water meter vaults and chlorination/testing. Sanitary sewer improvements consisted of 1,500 lf of 8” sewer line with depths averaging 12’.

Water & Sewer Replacement Project: Douglas, WY

Construction of this project included the complete reconstruction of water, sewer, storm drainage, concrete curb, sidewalks, aggregate sub-base and asphalt restoration for the city of Douglas.