Dickinson, North Dakota
JR Civil constructed all site improvements for a new Marriott Hotel location in Dickinson, ND. This project included 2,800 lf of 8” water main, 3,400 lf of 8” sanitary sewer, 35,000 CY of mass excavation and site grading, 12,000 tns of aggregate base course, curb & gutter construction, hotel foundation walls and base slab, sidewalk improvements, 2,890 lf of 18” storm drain improvements. All concrete improvements were performed in winter conditions requiring heat and cover with an on-time completion.
- Project Name: Marriott Hotel Improvements
- Project Location: Dickinson, North Dakota
- Project Value: $1,800,000